Vietnam: New points regarding the methods for management of a program/project funded by ODA

On October 01, 2018, the Government of Vietnam issued Decree No. 132/2018/ND-CP on amendments to a number of articles of Decree No. 16/2016/ND-CP. Notably, there are new points regarding the methods for management of a program/project funded by ODA.

Specifically, Decree No. 132/2018/ND-CP of Vietnam’s Government stipulates that program/project management shall be carried out according to the project document and the feasibility study report approved by a competent authority or a specific international treaty or agreement on ODA or concessional loan signed with the foreign donor. According to the scope, nature and conditions of the program/project, capacity of program/project management, the investment shall decide on either of the following methods:

- For a construction program/project: apply a management method that is conformable with regulations of law on construction project management.

- For other programs and projects:

+ Establishment of a new project management board;

+ Employment of the existing project management board to manage the new program/project;

+ Management by the project owner;

+ Full management of the program/project by the foreign donor;

+ Partial management of the program/project by the foreign donor.

- Partial or full management of the program/project by a third party.

More details can be found in Decree No. 132/2018/ND-CP of Vietnam’s Government, which takes effect from October 01, 2018.

-Thao Uyen-

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

1 lượt xem



Related Document
  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: [email protected]
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;