Circular 128/2016/TT-BQP was issued by the Ministry of National Defense on August 30, 2016, specifying the detailed steps for hoist testing of rocket launchers.
Accordingly, Circular 128 stipulates that technical safety inspection of lifting hoists must be carried out sequentially according to the following steps:
- Step 1: Inspect documents and records;- Step 2: External technical inspection;- Step 3: Technical inspection - No-load test;- Step 4: Load test policies - Testing methods;- Step 5: Process inspection results.
Note:
Subsequent inspection steps can only be performed if the results of the previous step meet the requirements. All results of each step must be fully recorded in the field log and fully stored at the inspection organization.
See details in Circular 128/2016/TT-BQP, which took effect from October 15, 2016.